LAWS(NCD)-1997-3-112

PRAHLAD NARAIN MATHUR Vs. RAJASTHAN HOUSING BOARD

Decided On March 18, 1997
PRAHLAD NARAIN MATHUR Appellant
V/S
RAJASTHAN HOUSING BOARD Respondents

JUDGEMENT

(1.) Un disputed facts are that although initially the complainant has got himself registered under Kalpatru Scheme of the Rajasthan Housing Boardtion under Parijat Self Financing Scheme, 1988 floated by the Housing Board. Under that Scheme allotment of house is assured within two years. Reservation letter was issued infavour of the complainant on 10.11.89 reserving a MIG A cate gory house infavour of the complainant at Sanganer. The complainant was required to de posit the approximate cost of the house by 4 six monthly instalments. The first instalment was to be deposited on 8.1.90 and the last instalment on 8.7.91. The complainant had deposited all the 4 instalments in time, but there was delay in allotment of house to the complainant. It was only on 28.2.94 that the Rajasthan Housing Board issued an allotment letter in favour of the complainant allotting to him house No.83/202 in Sanganer Scheme. After giving credit to the instalments which the complainant had deposited in pursuance of the reservation letter dated 10.11.89 and interest thereon @ 6% per annum, the complainant was further required to deposit an amount of Rs.1,20,202/ towards the cost of the house. According to the complainant, this cost is excessive, it is stated that cost which was in force in 1989 should have been levied. It is also stated that despite assurance for allotment of the house within two years given by the Parijat Self Financing Scheme, the allotment of the house has been made with great delay of about two years and three months. This has led to the increase in the cost of the house and the complainant has suffered loss. It is also stated by the complainant that he had to bear rent of the rented house on account of the delayed allotment of the house. The complainant has further claimed an amount of Rs.4 lacs as compensation for mental distress and agony.

(2.) Lately, the National Commission in First Appeal No.620/94 (Rajasthan Housing Board V/s. R. C. Bhandari, 1997 1 CPJ 27 (NC) has held that grant of interest at the rate of 15% for the period commencing from 1.4.90 and 30.4.92 in that case was against the contractual stipulation contained in para 6.5 of the Scheme in which it is clearly mentioned that in case the did not deliver the pos session of the house after construction within two years, it shall pay interest @ 6% p. a. commencing from after the expiry of two years till the delayed date for delivery of possession. The National Commission, therefore, held that the complainant was entitled to interest @ 6% p. a. We are bound by this decision of the National Commission.

(3.) From the allotment letter it appears that the Housing Board has already given to the complainant an amount of Rs.12,709.50 as interest on the instalment amounts deposited by the complainant @ 6% p. a. Thus the Opposite Party has already fulfilled its contractual stipulation of paying interest @ 6% p. a. commencing from the date after the expiry of two years till the delayed allotment. Consequently, the complainant is not entitled to interest for the delayed period at a rate more than 6% p. a. as held by the National Com mission. This is one aspect of the matter.