LAWS(NCD)-2022-9-10

PERVEZ AMIN Vs. KANPUR DEVELOPMENT AUTHORITY

Decided On September 19, 2022
Pervez Amin Appellant
V/S
KANPUR DEVELOPMENT AUTHORITY Respondents

JUDGEMENT

(1.) Heard Ms. Priyanka Sinha, Advocate, for the complainants and Mr. Abhishek Chaudhary, Advocate, for the opposite party.

(2.) 48 flat buyers have filed above complaint, as a representative case, for directing the opposite party to (i) handover possession of the flats to the complainants, complete in all respect as per specifications, forthwith, (ii) not to demand any amount other than as indicated in Brochure, (iii) to remove deficiency in construction in respect of use of marble and aluminium sink, (iv) to pay Rs.8000.00, per month as rent from due date of possession till delivery of actual possession, (v) to pay exemplary damage for mental agony and harassment, (vi) to pay compensation for delay in handing over possession, (vii) to pay the costs of litigation; and (viii) any other relief which may be deemed fit and proper in the facts and circumstances of the case. IA/1/2012 and IA/15414/2018 were allowed and permission to sue as a class action case under Sec. 12 (1) (c) of the Consumer Protection Act, 1986 was granted, vide order dtd. 9/11/2020. RA/189/2020, for review of order dtd. 9/11/2020 was rejected on 12/1/2021.

(3.) The complainants stated that Kanpur Development Authority (the opposite party) launched a project of group housing, namely "Ashiana Housing Scheme" at Jajmau, Kanpur City, in the year 2007 and made wide publicity of it. Under this project, four storied building, of 100 flats on each story (total 400 flats) had to be constructed for different categories of the persons as mentioned in the schedule. Registration for allotment was started from 1/11/2007 and last date for registration was 26/11/2007. Registration money was Rs.80000.00. Tentative cost of ground floor flats was Rs.9.30 lacs and other flats was Rs.7.75 lacs. Attracting with lucrative representation and believing on it, all the complainants applied for allotment of the flat and deposited registration money within time. Allotment was done by draw of lottery on 15/12/2007, in which, all the complainants were allotted flats under their category. Allotment Letters were issued to them on 5/2/2008 onward. According to clause 6.10 of the Brochure, 25% of tentative cost including registration money had to be deposited within 3 months from the date of issue of allotment letter and under Clause 6.20, remaining 75% of the cost had to be deposited in 3 equal three monthly instalments. Along with allotment letter, payment schedule was slightly changed and first instalment had to be deposited till 25/2/2008, second instalment till 25/4/2008, third instalment till 25/7/2008 and fourth instalment till 25/10/2008. Under clause-16.00, period of possession was given as 15 months and latest within 18 months from the allotment. The complainants timely deposited their instalments. Mrs. Shama Parveen (complainant-2) deposited an extra amount of Rs.253800.00 on 6/5/2009 under some confusion. In spite of payment of entire sale price within time, the opposite party could not deliver possession on promised date. When the possession was not offered on due date, Mrs. Shama Parveen gave an e-mail dtd. 23/3/2012, inquiring for possession from the opposite party. The opposite party, vide letter dtd. 6/6/2012, informed her that she was not depositing her instalments and required her to deposit dues forthwith and if the instalments was deposited then to produce its receipts within 7 days. In local newspaper dtd. 12/7/2012, a news was published that the project "Ashiana Housing Scheme" was incomplete and hard earned money of flat buyers was blocked. Immediately thereafter, the opposite party issued demand letters dtd. 20/7/2012, to the complainants demanding extra-amount. Mrs. Shama Parveen, through an application dtd. 27/8/2012, sought for information inter-alia that on the basis of which Government Order/ Rules, costs of the flats were enhanced, under Right to Information Act, 2005. Executive Engineer, vide letter dtd. 1/10/2012, informed that "Ashiana Housing Scheme" was for the persons of "High Income Group"; in the Brochure, tentative costs were mentioned and after completing construction, final costing was done according to the guide-lines of the government; the construction was delayed due to stay orders of the High Court and due to damage of culvert near KESA office due to laying down of sewer pipeline under JNURM scheme. As information in respect of final costing was vague, Mrs. Shama Parveen filed an appeal on 3/10/2012, for supply of full information but it was not supplied. Mrs. Shama Parveen, through her application dtd. 1/11/2012, sought for inspection of the records, inter-alia of Final Costing Records, under Right to Information Act, 2005. Some of the complainants moved representation dtd. 4/9/2012 and reminder dtd. 3/10/2012 before District Magistrate, for taking back of the increased price and handover possession to all the allottees. The complainants moved a representation dtd. 27/9/2012, to Vice-Chairman of the opposite party for handing over possession of the flats to the allottees and withdrawing demand of enhanced price. The complainants moved a representation dtd. 3/10/2012, to Hon'ble Chief Minister, for handing over possession of the flats to the allottees and withdrawing demand of enhanced price. The complainants stated that due to stay order of High Court, 253 flats were constructed instead of 400 flats and explanation for delay was incorrect. Alleging that the opposite party has committed deficiency in service, the complaint was filed on 22/11/2012, inasmuch as the construction of the project was unreasonably delayed due to which, cost was increased; the allottes were not liable to pay any enhanced cost as they had already made full payment in the year 2008 and the construction was not done as per specifications.