LAWS(JHAR)-2006-3-101

CENTRAL COALFIELDS LIMITED Vs. MAHABIR PRASAD RUNGTA

Decided On March 22, 2006
CENTRAL COALFIELDS LIMITED Appellant
V/S
Mahabir Prasad Rungta Respondents

JUDGEMENT

(1.) ST appellant M/s Central Coalfields Limited (hereinafter to be referred as Company) and others have preferred this appeal against the order dated 24th March 2003 passed by the learned Single Judge in W.P.(C ) No. 6006 of 2002, whereby and whereunder the learned Single Judge while held that in the change position the Court cannot direct that the 1st respondent - writ petitioner be remedied by lifting linkage slurry and thereby refused to grant relief to that extent; further held that the 1st respondent -writ petitioner having been discriminated will be entitled to damage and gave liberty to the appellant to escape from such liability by providing slurry to the 1st respondent - writ petitioner on the terms and condition on which it was made available to the 6th respondent, M/s Bharat Coal Products, Bokaro.

(2.) AS the appeal may be disposed of on the short point, it is not necessary to discuss all the facts except the relevant one.

(3.) THE 1st respondent - writ petitioner in the meantime was purchasing coal slurry from open market at higher rate, no linkage having been issued for lifting coal slurry from Kathara colliery as per direction of Coal Controller of India. Thereafter, the 1st respondent -writ petitioner preferred the writ petition in question, in which prayer was made to direct the Company to grant permanent linkage in his favour for lifting slurry from Kathara washery at the rate of 60,000/ -M.T. per year; further prayer was made to Page 868 declare that he was entitled to such permanent linkage w.e.f. 11th December 1994 i.e. the date on which the coal linkage was allowed in favour of 6th respondent herein.