LAWS(JHAR)-2002-8-80

PROJECT AND DEVELOPMENT INDIA LTD. Vs. PRESIDING OFFICER

Decided On August 28, 2002
Project And Development India Ltd. Appellant
V/S
PRESIDING OFFICER Respondents

JUDGEMENT

(1.) THIS appeal under Clause 10 of the Letters Patent is directed against a judgment and order dated 05.03.98 passed by learned Single Judge of this Court in C.W.J.C. No. 3834 of 1995R whereby the learned Single Judge directed the appellant to pay current wages under Section 17B of the industrial Disputes Act, 1947, to respondent No. 2 without realizing penal rent from him with respect to the occupation of the quarter by him.

(2.) RESPONDENT No. 2 was an employee of the appellant at one time. He was served a charge -sheet and on the basis of a domestic enquiry, an order was passed on 19th June, 1992, discharging him from service. This order being challenged before the Labour Court, Dhanbad, having been set aside by the Labour Court, Writ Petition being C.W.J.C. No. 3834 of 1995R was filed by the appellant in this Court challenging the aforesaid award of the Labour Court. By judgment pronounced today by us, that Writ Petition has been allowed and the award of the Labour Court set aside, consequentially the discharge order dated 19th June, 1992 having been upheld and affirmed.

(3.) LOOKING at from any angle, therefore, the order dated 05.03.1998 passed by the learned Single Judge cannot be justified. This order is, accordingly; set aside with all consequences. The appeal is allowed. No order as to costs.