LAWS(JHAR)-2011-5-43

MADAN LAL BAJAJ CONSTRUCTION Vs. STATE OF JHARKHAND

Decided On May 11, 2011
Madan Lal Bajaj Construction Appellant
V/S
STATE OF JHARKHAND Respondents

JUDGEMENT

(1.) The present writ petition has been preferred mainly for the reason that the Petitioner is one of the bidders for construction of two godowns having capacity of 2500 metric tones, for storage of foodgrains and fertilizers and one more godown having a capacity of 1000 metric tones in the campus of Agricultural Produce Market Committee, Jamtara. The tender notice is at Annexure-1 to the memo of the petition, which is dated 22nd December, 2010.

(2.) It has been submitted by the counsel for the Petitioner that the Petitioner has offered the price for the construction of the aforesaid godowns at Rs. 1,73,86,860.25p against the estimated cost of the godowns published in the tender, which is at Rs. 2,16,31,400/-. Thus, against the aforesaid estimated cost, the Petitioner is ready and willing to construct the aforesaid godowns with 15% lesser amount in competition with other bidders. The Petitioner was decided to allot the work by the Respondents by a letter dated 27th January, 2011 (Annexure-2 to the memo of the petition), but, to the utter surprise of the Petitioner without cancelling the aforesaid letter of intent Issued in favour of the Petitioner and without assigning any reason to the Petitioner and without giving any notice to the Petitioner, abruptly, arbitrarily and unilaterally the notice inviting tender dated 22nd December, 2010 (Annexure-1) was cancelled and a fresh notice inviting tenders was published on 28th February, 2011, which is at Annexure-4 to the memo of the petition, which is under challenge in this writ petition mainly on the ground that the Petitioner is ready and willing to complete the work against estimated cost of Rs. 2,16.31,400/-for Rs. 1,73,86.860.25p.

(3.) Counsel for the Respondents-State submitted that there is a breach of Clause-18 of the condition, which reads as under: