LAWS(TLNG)-2018-11-14

SAI RAM CONSTRUCTIONS Vs. STATE OF TELANGANA

Decided On November 20, 2018
Sai Ram Constructions Appellant
V/S
State of Telangana Respondents

JUDGEMENT

(1.) On 06.09.2018 Online tender notification was issued calling for bids to undertake the job of repairs and restoration of Rallavagu and Rallavagu Pick up Dam, Karegattu village, Paloncha Mandal, Bhadradri Kothagudem district as part of Mission Kakatiya Phase-IV Project. The Estimated Contract Value (ECV) was 41,29,10,539/-. The bid validity period prescribed as three months and time for completion of work as 24 months. Clause-17 of the tender notification prescribes submission of solvency certificate. Petitioner submitted his bid. He has obtained solvency certificate issued by the Indian Overseas Bank on 19.09.2018 certifying that petitioner can be treated as good up to a sum of 42.00 crores. Technical bids were opened on 20.09.2018 and the evaluation was completed by 26.09.2018. On 26.09.2018 petitioner was informed that the tender submitted by the petitioner was not accepted on the ground that the solvency certificate was conditional and, therefore, not acceptable. Challenging the same, this writ petition is filed.

(2.) Heard learned senior counsel Sri A.Sudarshan Reddy appearing for Sri G.Madusudhan Reddy, counsel for petitioner, learned senior counsel Sri K.G.Krishna Murthy for 5th respondent and the learned Government Pleader for respondents 1 to 4.

(3.) According to learned senior counsel Sri A.Sudarshan Reddy rejection of tender on the ground that solvency certificate is conditional is illegal and amounts to arbitrary exercise of power.