(1.) HEARD learned counsel for the parties.
(2.) THIS writ petition seeks to challenge the order dated 24. 3. 2004 by which petitioner was removed from the post of Sarpanch on the allegation of financial irregularities and recovery of a sum of Rs. 4,39,787- was directed to be made from him.
(3.) IN the present case, respondents have not been able to prove to the satisfaction of the Court that whether in fact the requirements of the said rules were adhered to or not or the petitioner was associated in completion of the civil work done which was actually executed though their Engineers and payment was also released on verification by them.