(1.) THIS revision petition is directed against the order dated 16.12.1995 and 8.8.1995 respectively passed by the District Judge, Sikar and Civil Judge (Senior Division) Danta Ramgarh, whereby the application under Order 39 Rules 1 and 2 CPC by the plaintiff non -petitioner has been allowed.
(2.) BRIEF facts are that the plaintiff instituted a civil suit in the trial court along with an application under Order 39 Rules 1 and 2 CPC stating therein that he applied for 'one Pole Scheme connection' and for that purpose he deposited Rs. 1,000/ - with the Assistant Engineer. RSEB Danta Ramgarh. The Board had released certain connections in serial order and the plaintiff non -petitioner has been placed at No. 1, but the employees of the Board wanted to breach the priority and are releasing the connections to others, as such the Board be restrained from releasing electric connections to any body else in breach of priority of the present non - petitioner.
(3.) THE trial court vide the impugned order issued temporary injunction in favour of the plaintiff non -petitioner. The defendant petitioner preferred to appeal against the said order but the same was also missed.