(1.) THIS is a civil revision directed against the judgment of the learned District Judge, Jaipur City, Jaipur dated January 20, 1973 whereby he has modified an order of injunction dated June 3, 1972,
(2.) THE facts which it is necessary to recall for the disposal of this revision application, briefly stated are these In Bani Park Jaipur the Urban Improvement Trust (hereinafter called 'the U.I.T') prepared a scheme called 'Paramvir Major Shaitan Singh Scheme' for construction of a colony. Prem Dayal and Babu Lal Sharma, petitioner -plaintiffs before me, purchased two plots in auction bearing Nos. 76 and A.8 respectively. In the said scheme there was left, the petitioner -plaintiffs alleged, a triangular open space of land which they claimed was intended to be a park. In 1969 the U.I.T. allotted that plot bearing No. 26 measuring 80' x 120' to one Vipin Prabhakar. The plaintiffs alleged that plot No. A 26 encroached on the land intended to be the park. Complaints were made to the U.I.T. but without success and, therefore, the petitioner -plaintiffs instituted a suit against Vipin Prabhakar and others for injunction. The learned Munsif issued an exparte ad -interim injunction on December 1, 1971 to the effect that the U.I.T. shall not give permission for constructing a house in any part of the land marked in the site plan and reserved for a park. Likewise, Vipin Prabhakar was also restrained from raising any construction thereon. The ex -parte injunction was vacated by the learned Munsif on December 6, 1971 The petitioner -plaintiffs before me went up in appeal in the Court of the District Judge, Jaipur, who by his order dated June 3, 1972, accepted the appeals and set aside the order of the learned Munsif dated December 6, 1971, and confirmed the Ex. parte injunction issued by him on December 1, 1971. In the course of arguments before the learned District Judge it was urged on behalf of Vipin Prabhakar that the scheme had been altered and the plot No. A26 in the altered scheme encroached upon the space meant for park only by 20' and the rest of the 60' remained undisputed and there should be no objection in letting the defendant No. 3 Vipin Prabhakar to construct upon the area of 60' x 120' of the plot. The learned District Judge observed that he could not make any pronouncement at that stage because it was not certain whether the U.I.T. will agree that the size of the plot should be reduced in this building line.
(3.) MR . Sharma on behalf of the respondent No. 3, has raised a preliminary objection that the present revision application is not competent in as much as the jurisdiction exercised by the learned District Judge was neither illegal nor it was exercised with material irregularity. He placed if liance on Hindustan Aeronautics Ltd., Balanagar, Hyderabad and Anr. v. Ajit Prasad Tarway : (1972)ILLJ170SC .