LAWS(J&K)-2021-9-56

UNION OF INDIA Vs. GEE KAY ENGINEERING INDUSTRIES

Decided On September 16, 2021
UNION OF INDIA Appellant
V/S
Gee Kay Engineering Industries Respondents

JUDGEMENT

(1.) The Petitioner has challenged the impugned interim Award dated 04.01.2020 passed by the sole Arbitrator, the operative part of which is as under :

(2.) Briefly stated the case of the respondent-firm before the learned Arbitrator was that being a supplier of defence equipments to the Indian Army and Para Military Forces, it was given a contract for supply of 6250 pairs of Boot Anti Mine Infantry (hereinafter referred to as 'BAMI') in terms of Order No. 21023/Supply order/110 (C/ACSFO/45) dated 01.03.2018. As per clause Part IV i.e Special conditions of supply order of the Tender Agreement, the appellant herein had to make the payment to the respondent-firm instantly. For facility of reference, the said clause is reproduced hereunder:

(3.) It was further alleged by the respondent-firm that in the instant case, no payment has been made to the said firm till date. The respondent-firm had taken credit limit from the Axis Bank for the aforesaid supply and because of the delay in the payment, it has suffered a grave financial hardship. That apart, the Bank aforesaid was ready to initiate action for declaring the respondent- firm as NPA under the Scrutinization Act. The respondent-firm is stated to be paying huge interest to the Bank for non payment of loan amount and has paid a total amount of Rs.1,94,00,000/- as interest from July 2018 to September, 2019. The claimant has also pledged his property with the Bank.