(1.) The Himachal Pradesh State Electricity Board (for short HPSEB1) has filed this petition under Article 227 of the Constitution of India, challenging the order dated 12.3.2004 marked (Annexure P -3) and order dated 25.3.2004 marked (Ext. P -5) recorded by sole Arbitrator (respondent No. 2) herein whereby cost -of Rs. 15,000/ - was imposed upon the petitioner -Board during the arbitral proceedings and its application under Sections 12(3) and 13 of the Arbitration and Conciliation Act, 1996 has been dismissed.
(2.) The petitioner -Board and respondent No. 1 had entered into a agreement for the construction of civil work comprising Intake Structure, Link Tunnel, underground Desilting Tank etc. etc. in Distt. Kangra, vide Agreement No. 1/91 dated 21.2.1991. The stipulated time for completion of the said work was for 24 months. Respondent No. 1 -claimant, however, could not complete the said work within the agreed time. Time was extended to the claimant from time to time after reserving the right of the petitioner -Board to recover liquidated damages for the delay in the completion of the works and as such the work finally be completed on 8.4.1997.
(3.) The petitioner -Board imposed compensation for delayed completion of work under Clause 2 of the Agreement amounting to Rs. 68,00,000/ -. A Civil Suit No. 3/200 has been filed before this Court which is pending adjudication.