LAWS(GAU)-2002-6-33

UNION OF INDIA Vs. MAJOR V P NIJHAWAN

Decided On June 19, 2002
UNION OF INDIA Appellant
V/S
MAJOR V.P. NIJHAWAN Respondents

JUDGEMENT

(1.) Heard Mr. J Singh, learned senior counsel for the appellant and Ms. G. Deka, learned counsel for the Respondent.

(2.) This arbitration appeal is filed by Union of India [Railways] challenging the order passed by the Civil Judge, Senior Division No. 1, Guwahati dated 16.3.2001 passed in Misc [J] Case No. 154/2000 arising out of TS [Arb] Case No. 229/95 where under he has remitted the matter for fresh adjudication by the sole Arbitrator in respect of interest on items Nos. II, III, IV and V holding that the decision of the Arbitrator in not awarding interest on the said items is not in accordance with law. It is submitted by the learned counsel for the Union of India that on account of sub-clause [3] of Clause 16 of the General Conditions of Contract the contractor is not entitled for award of the interest and thus the Court has committed an error in setting aside the award so far it related to non-grant of interest to the contractor. Clause 16, sub-clause [3] reads as under:

(3.) It is obvious from sub clause [3] that no interest will be payable upon the earnest money, security deposit or the amount payable to the contractor under the contract. Thus sub-clause [3] prohibits the contractor from making any claim in regard to interest on the amount of earnest money, security deposit or any amount due to the contractor under the contract. There appears to be complete prohibition of grant of interest by virtue of sub-clause [3] of clause 16 of the General Conditions of Contract. In a majority decision rendered by the constitution Bench of the Apex Court, reported in [2001] 2 SCC 721 [Executive Engineer, Dhenkanal Minor Irrigation Division, Orissa & Ors V/s N C Budharaj (deceased) by LRs & Ors] in para 26 it has been held that the Arbitrator has jurisdiction to award interest, on the sums found due and payable, for the pre-reference period, in the absence of any specific stipulation or prohibition in the contract to claim or grant any such interest. Thus the Arbitrator has the jurisdiction to grant interest on the sums found due and payable for the pre-reference period, but it will be subject to - in the absence of any specific stipulation or prohibition in the contract to grant any such interest. If there is any such specific terms in the contract, prohibiting award of interest, the Arbitrator does not have any authority to grant interest.