(1.) The twenty-three petitioners in this writ petition dated October 9,2001 are aggrieved by the decision of the Central Government dated September 19, 2001, Annexure P-9 at p. 132,
(2.) Mr. Bhattacharya, counsel for the petitioners, has drawn my attention to the findings of the Assistant Labour Commissioner (Central), Calcutta - III recorded in his enquiry report dated April 7, 2000, Annexure P8 at p. 127, which are as follows: "From the above facts and circumstances, the following observations have been made:
(3.) The same contractor is engaged by the management of Haldia Dock Complex' (CPT), probably because they could get the job in all the time till date though the contract is awarded periodically by inviting open tenders.