LAWS(CAL)-2012-7-26

LARSEN & TOUBRO LTD Vs. VISA POWER LTD

Decided On July 12, 2012
LARSEN AND TOUBRO LTD Appellant
V/S
VISA POWER LTD Respondents

JUDGEMENT

(1.) THE Court : In view of lawyers not being present, Mr.K.M. Subramanium, a Project Director of Larsen and Toubro Limited, the appellant abovenamed company assisted by Mr.S.K. Bhatt, Chief Legal Advisor of the appellant company argues the matter. Despite notice being given, the respondent is absent.

(2.) THIS appeal emanates from the judgment and order dated July 10, 2012 passed by the learned Single Judge dismissing the application made under Section 9 of the Arbitration and Conciliation Act, 1996, inter alia, asking for injunction restraining the respondent from encashing or invoking the bank guarantee that was furnished by the appellant in favour of the respondent as and by way of guarantee to the performance in respect of a contract entered into by the parties for setting up a power plant in the State of Chattisgarh. Mr. Subramanium submits that despite a sum of Rs.140 crores approximately still due and payable from the respondent by the appellant, the appellant did not stop their work. Even then the respondent attempted to encash the performance guarantee that gave rise to the proceeding before the learned Single Judge. At the initial stage, the respondent's Counsel assured the Court that they would not encash the same till the matter was heard. Subsequently, the matter was heard at length and dismissed by His Lordship by the judgment and order passed on July 10, 2012 impugned herein.

(3.) THE application is made returnable tomorrow, i.e., July 13, 2012. Let a further notice be served upon the learned Advocate for the respondent.