LAWS(APH)-2005-11-96

C SHASHI KUMAR Vs. GOVERNMENT OF A P

Decided On November 22, 2005
C.SHASHI KUMAR Appellant
V/S
GOVERNMENT OF A.P Respondents

JUDGEMENT

(1.) The Government Memo No.7978/M.II(1)/2004-1, dated 20.9.2004, was challenged by the appellant by way of writ petition No.20420 of 2004. The writ petition has been dismissed. Hence, this appeal.

(2.) We have perused the record and heard learned Counsel for the parties.

(3.) The facts leading to filing of the writ petition and writ appeal are that one Dr. Aluri Prabhakara Rao applied for grant of mining lease. He was granted prospecting licence over an extent of eight hectors in Survey Nos.910/P, 916 and 917 of Pothakamur Village, hamlet of Batlapalem Village, Darsi Mandal, Prakasam District, for a period of two years. He was required to execute prospecting licence deed within a period of 90 days as per the provisions of the Andhra Pradesh Minor Mineral Concession Rules, 1966 (hereinafter referred to as 'the Rules'). He approached the Director of Mines and Geology, Government of Andhra Pradesh, Hyderabad for extension of time for execution of prospecting licence deed. The Director of Mines and Geology, on 29.6.2002, granted first extension of time for a period of thirty days for execution of the deed. The deed was not executed within the extended period of time and 4th respondent again requested for extension of time. The Director, Mines and Geology gave another extension, but the 4th respondent again failed to execute the prospecting licence deed within fifteen days. Thereafter, the Director of Mines and Geology, by his order dated 17.9.2003, revoked the lease. This order of the Director of Mines and Geology was challenged by way of a revision before the Government under Rule 35-A of the Rules. The Government entertained the revision and granted two months time to the 4th respondent for execution of the prospecting licence deed and set aside the order of the Director of Mines and Geology. While granting extension, the Government put the condition that request for further extension of time in future would not be entertained under any circumstances and if there was failure to execute the licence deed, the Director of Mines and Geology's order dated 17.9.2003 would automatically revive. In spite of this order, the 4th respondent did not execute the deed and filed a fresh petition before the Government, which is the impugned order in the writ petition. This order refers to the earlier orders and then says-