LAWS(BOM)-1989-3-12

CHLORIDE INDUSTRIES LTD Vs. UNION OF INDIA

Decided On March 21, 1989
CHLORIDE INDUSTRIES LTD. Appellant
V/S
UNION OF INDIA Respondents

JUDGEMENT

(1.) RULE returnable forthwith. Respondents waive service.

(2.) DELAY of 16 days in the filing of the appeal in question was not condoned by the Tribunal. Hence this petition.

(3.) NOW, it is very difficult for this Court to exercise its discretionary powers to interfere with the matter which itself is basically discretionary and when the said discretion could not be said to have been exercised arbitrarily. In this case, however, we find that the appeal is filed not against any demand as such but on the question of refund sought to be claimed by the petitioner company and this claim for refund runs into, what we are informed at the bar, over Rs. 40 lacs. The delay again has occurred not because of any sheer negligence or neglect on the part of the petitioners but because of certain circumstances not entirely within the control of the petitioners. The legal advice and opinion obtained from an Advocate who later shifted to Delhi and the legal advice obtained from a subsequent Advocate, through not very cogent reasons for condoning the delay, are nevertheless factors which cannot be said to be totally irrelevant. The delay again is not gross but, as indicated, of 16 days. We also cannot overlook the weighty observations of the supreme Court in Collector, Land Acquisition, Anantnag v. Kateji - 1987 (28) E. L. T. 185 (S. C.)= AIR 1987 S. C. 1352 on which, naturally, heavy reliance has been placed by the petitioner's learned Counsel Mr. Avinash Shivade. These observations have been quoted at page II of this petition. In the context of all these circumstance, we are inclined to condone delay and permit the petitioners to have their claim adjudicated on its own merits and in accordance with law but on payment of exemplary costs as directed below.