(1.) A notice inviting tenders for the construction of a bridge across Nilkantha River in File No. 7/7 of Barsi Tuljapur Road, was issued by the Executive Engineer of Sholapur (B. and C. Division). The estimated cost was Rs. 4,09,185 and 24 months were allowed as the time for execution of the work. The tender of Messers. S.N. Chawhan, a partnership firm of 560/69, South Sadar Bazar, Sholapur, was accepted. It was an item rate contract and rates for separate items such as excavation for foundation, diversion of water course and providing coffer dam, providing fabricating and setting out steel cutting edges for reinforced cement concrete wall curbs, providing and casting in situ cement concrete, sinking of foundation walls, bottom plug for walls, etc. were agreed upon. The work order was placed on 10-1-1967 and though the period of completion was 2 years the work was completed in December, 1970. As there was delay in executing the work, the Executive Engineer imposed a penalty of Rs. 13,080/- in the final bill. The contractor filed Special Civil Suit No. 76 of 1972 against State of Maharashtra for refund of the penalty with interest in the Court of the Civil Judge (Senior Division), Sholapur, who partly decreed the same to the extent of Rs. 13,080/-. Aggrieved, the State of Maharashtra comes up in appeal.
(2.) In a case like the present one, in order to pronounce upon the responsibility of delay in execution of the work, the test to be applied is contained in sections 52 to 55 of the Contract Act, relating to reciprocal promises. Section 52 provides that reciprocal promises have to be performed in that order which the nature of the transaction requires. Under section 53 if a party to the contract prevents the other from performing his promise, the contract becomes voidable entitling the aggrieved party to claim compensation. Under section 55 which deals with the contracts, where time is of the essence the promise is entitled to compensation from the promisor if the latter fails to perform certain things at or before specified times.
(3.) After the work order was issued on 19th January, 1967 the contractor vide Exh. 58 dated 14-4-1967 informed the Dy. Engineer, Barsi, that he has made preliminary arrangements for starting the work but requested the Engineer to spare some time for personal discussion of the work programme and "marking lining out of work". In this letter the contractor also referred to an earlier letter dated 30th January, 1967 i.e. issued within 10 days of having received the work order on the same subject. No reply was sent to the 30th January letter nor Exh. 58, for a fairly long time in between, on 14th July, 1967 vide Exh. 59, the contractor requested for detailed measurements and drawings of R.C.C. curbs, stating dimensions of range etc. This was replied to on 4th August, 1967 Exh. 60 when the Executive Engineer expressed surprise about the complaint of non-supply of the drawings when they had been already, supplied. During the course of the trial, the plaintiff had called upon the defendant to produce the record showing as to when detailed measurements and drawings were supplied, but the defendants did not produce any record.