LAWS(ALL)-2004-5-82

HINDUSTAN LEVER LTD Vs. PRESIDING OFFICER INDUSTRIAL TRIBUNAL

Decided On May 28, 2004
HINDUSTAN LEVER LTD. Appellant
V/S
PRESIDING OFFICER, INDUSTRIAL TRIBUNAL NO.V, MEERUT Respondents

JUDGEMENT

(1.) Heard Sri Sudhir Chandra, senior counsel assisted by Ms. Bharti Sapru, counsel for the petitioner and Sri K. P. Agarwal, senior counsel appearing for the respondents and perused the record.

(2.) This writ petition is directed against an order dated August 8, 2003 passed the Presiding Officer, Industrial Tribunal V, U.P. Meerut in an application filed by the Management in Adjudication Case No. 42 of 1998 praying for answering the reference that no industrial dispute survived between the parties in view of the registered settlement arrived at between the parties and the dispute has become stale by efflux of time. A settlement dated December 31, 1974 was arrived at between the petitioner and its workmen represented by Lever Karamchari Union. By the agreement dated December 31, 1974 it was agreed that the dearness allowances which was calculated on the basis Delhi working class cost of living index would not be paid over and above 1450 points. The parties also agreed that the Voluntary Separation Scheme which was expiring on December 31, 1974 would be extended. Some of the workmen represented by Hindustan Lever Mazdoor Sabha did not agree with the settlement dated December 31, 1974 aforesaid. They filed applications under Section 33-C(2) of the Industrial Disputes Act, 1947 before the Labour Court, Meerut claiming dearness allowance at the rate that was applicable prior to January 1, 1975 Respondent No. 2, Hindustan Lever Mazdoor Sabha and not signed the settlement dated December 31, 1974 but it was registered under Section 6-B of the U.P. Industrial Disputes Act. However, in 1977 there were negotiations between the petitioner and the respondent No. 2 and a large package of benefits to be given to the workmen was agreed. Respondent No. 2 Hindustan Lever Mazdoor Sabha agreed to ratify the settlement dated December 31, 1974 and also to withdraw its claim made in application under Section 33-C(2) of the Industrial Disputes Act, 1947. Thereafter a settlement dated December 5, 1977 was entered into between the petitioner and Hindustan Lever Mazdoor Sabha by which the ceiling imposed on the dearness allowance on the basis of Delhi working class cost of living index up to a maximum of 1450 points vide settlement dated December 31, 1974 was specifically agreed to and ratified. The relevant portion of the settlement dated December 5, 1977 entered into between the petitioner and the Hindustan Lever Mazdoor Sabha is as under:

(3.) These settlements were registered under Section 6-B of the U.P. Industrial Disputes Act by the Registering Authority. The counsel for the petitioner submits that the ceiling imposed on dearness allowance by the settlement dated December 31, 1974 remained in force only up to January 3, 1977 i.e. when the settlement dated December 5, 1977 came into force. It is further submitted that even after settlement dated December 5, 1977 subsequent settlements were entered into between the parties and the dearness allowance was revised from time to time as per the terms of the respective settlements and they were relied upon by both parties. In compliance with clause 14 of the settlement dated December 5, 1977 all the workmen except one Sri Bidani withdrew the applications under Section 33-C(2) of the Industrial Disputes Act, 1947 which were filed before the Labour Court. It is urged that the subsequent settlements also reiterated that the terms of the settlement dated December 31, 1974 would be final and binding on the Sabha and it would not raise any dispute with respect to the same and that in fact the settlement dated May 3, 1991 specifically mentioned that Hindustan Lever Mazdoor Sabha would pray for a no dispute award with regard to the dearness allowance.