LAWS(NGT)-2015-7-4

DHARMARAJAN Vs. THE DISTRICT COLLECTOR AND ORS.

Decided On July 31, 2015
DHARMARAJAN Appellant
V/S
The District Collector and Ors. Respondents

JUDGEMENT

(1.) THE counsel for the parties are present. The case of the applicant, in short, is that the applicant and his brothers own property at Survey No. 284, Kondampatti Village, Pollachi Taluk. The land is fertile and the applicant along with his family members is carrying on the agricultural operations. The 4th respondent after obtaining permission from the respondents 1 to 3 started the coir mill in the year 2004. At the initial stage the applicant did not raise any objection. But when the 4th respondent Unit caught fire, 60 coconut trees belonging to the applicant were also burnt. In view of the health hazards caused by the said Unit, the applicant and the members of the family underwent medical treatment. Aggrieved over the generation of noise as well as air pollution by the coir industry of the 4th respondent situated at Survey No. 285/2 adjacent property of the applicant, representations were given. The pollution has caused enormous damage to the standing crops in the field. Pursuant to the complaint given by the applicant, the authorities of the Tamil Nadu State Pollution Control Board (Board) made inspection following the procedures and cancelled the licence and ordered closure on 19.4.2012. When a request was made by the 4th respondent, the Board authorities of the granted in 3 months time to implement pollution control measures but it was not performed by the 4th respondent as assured. Despite the said period was over, the 4th respondent even without taking the measures has been carrying on the operation of the coir Unit and the problems of both by noise and air pollution continues. Hence there arose a necessity to approach the Tribunal.

(2.) ON the above averments made, the applicant has sought for a direction to the respondents 1 to 3 to take appropriate action against the 4th respondent and also the closure of the coir Unit.

(3.) BUT the Counsel for the applicant reiterated the original complaint of pollution. While the matter stood so, it was reported on 7.5.2014 by the counsel for the 4th respondent that the period covered under the Consent order was over, pursuant to which the electricity service connection was also disconnected and the Unit was not running at that time. It was also brought to the notice of the Tribunal that the application for renewal was already filed even before the Consent period ended but the same was not considered by the Board. The learned counsel for the 4th respondent submitted that since all preventive and safeguard measures were already taken which were to the satisfaction of the officials of the Board, a direction is required to the Board to consider the application and pass orders thereon. A direction was issued to the Board to find out whether all the preventive and safeguard measures to control pollution were taken. Pursuant to the direction of the Tribunal, a report was filed on 29.5.2014 that an inspection of the coir industry of the 4th respondent was made in the presence of the 4th respondent on 20.5.2014. The Tribunal was not satisfied with the report and on the next hearing the DEE concerned appeared and filed a fresh report after making an inspection. Both the parties were given opportunity to make their comments on the report. In the meanwhile, the Consent to carry on the operation was granted to the 4th respondent Unit on the strength of which he commenced the operation of the coir Unit. Pointing to the Consent given to the 4th respondent, the counsel for the applicant pointed out that there are three main conditions attached therewith were not complied with by the 4th respondent and so long as the conditions were not complied with, the 4th respondent should not be permitted to carry on its operation. On the contrary, the 4th respondent submitted that all the conditions were complied with. From the report of the DEE concerned, it was quite evident that pursuant to the inspection made in order to prevent the dust pollution the 4th respondent was advised to raise the compound wall to the entire length on the eastern side. It was also reported that a major part of the compound wall was raised and the remaining was to be completed. At that juncture, the counsel for the 4th respondent placed a request for time to complete the same. On two occasions, time was granted on request. On 15.5.2015 it was reported by the counsel for the Board that all the preventive measures regarding pollution in question and the construction of wall were completed and sought time for filing report. Today, a report is filed by the 2nd and 3rd respondents which are Board and the DEE concerned. It would be more apt and appropriate to reproduce that part of the report which would be an answer to the application. Paragraph 3 of the report which reads as follows: