LAWS(MAD)-2013-1-297

ENERGO ENGINEERING PROJECTS LTD Vs. AISHWARYA CONSTRUCTIONS

Decided On January 28, 2013
Energo Engineering Projects Ltd Appellant
V/S
Aishwarya Constructions Respondents

JUDGEMENT

(1.) The present Civil Miscellaneous Appeal has been filed by M/s. Energo Engineering Projects Ltd., rep. by its Senior Vice President, Mr. Randhir Grover, NTPL Power Plant, Thoothukudi, challenging the impugned order passed by the learned District Court, Thoothukudi, in I.A. No. 392 of 2012 in Ar. O.P. No. 470 of 2012 dated 27.11.2012. The controversy before this Court is when the 2nd Respondent, Neyveli Tamil Nadu Power Limited (hereinafter referred to as NTPL), Thoothukudi, has given a contract in respect of erection/construction of Thermal Power Plant to the Appellant, in turn the Appellant has given sub contract to the 1st Respondent/Sri Aishwarya Constructions, Neyveli. During the execution of the work by the 1st Respondent, there was a failure of one of the rafts. In view of that, the 1st Respondent was directed to go for core cutting test. In the meantime, the 1st Respondent has also submitted payment of bills of which a sum of Rs. 16,35,000/- alone was paid. The two number of batching plants were procured by the 1st Respondent for which the 1st Respondent incurred a cost of Rs. 40 lakhs. Complaining that there was a delay in payment of Bills, problems were cropped up between the Appellant and the 1st Respondent, as a result, citing the reason that the 1st Respondent has not completed the expected work, the Appellant has issued termination letter dated 21.11.2012, terminating the work order given to the 1st Respondent. Aggrieved by the same, the 1st Respondent has approached the Trial Court namely, the District Court, Thoothukudi, by filing a Petition in Ar. O.P. No. 470 of 2012 along with I.A. No. 392 of 2012, under Order 39, Rule 1 & 2 of the Civil Procedure Code, taking a main ground that without any prior notice, the Order of Termination dated 21.11.2012 has been passed arbitrarily, which is impermissible in law. Ultimately, accepting the case of the 1st Respondent, the learned Trial Court has passed the impugned order dated 27.11.2012, granting three directions namely:

(2.) Learned Counsel for the Appellant would heavily contend that when there is a contract of work by registered Agreement dated 17.6.2011 entered into between the Appellant and the 1st Respondent specifically saying that in case of any dispute or difference of opinion during the course of execution of work, the party aggrieved by the terms and conditions should approach only the Arbitrator, but ignoring the same, the 1st Respondent has approached the Trial Court seeking injunction and the learned Trial Court also without giving a short notice to the Appellant and the 2nd Respondent erroneously granted injunction as a result, the work given by the 2nd Respondent to the Appellant in respect of erection/construction of Thermal Power Plant has been completely jeopardized, due to which, not only the Appellant but also the 2nd Respondent is put to great prejudice. Besides, since the work which pertains to construction of Thermal Power Plant for the welfare of the State is delayed due to the pendency of the case, the people of this state would also suffer the continuous scarcity of electricity.

(3.) Secondly, the learned Counsel for the Appellant contended that when the 1st Respondent can adequately be compensated in terms of Section 14(1)(a) of the Specific Relief Act, 1963, the Trial Court ought not to have granted injunction.