(1.) Aggrieved over the Award passed by the sole Arbitrator, the present Petition has been filed challenging the Award.
(2.) Brief fact leading to file this Original Petition is as follows:
(3.) It is the case of the Respondent that in pursuant to the direction to the Railway Board, the Claimant and Respondent have mutually agreed to implement the revised norms with effect from 1/10/1996 and also agreed that the said agreement shall be varied and/or added to in the manner hereinafter mentioned. Accordingly, Rider Agreement with revised input norms and revised formula for price variation was executed with implementation effective from 1/10/1996. There is no dispute regarding the date of implementation of revised norms. Both Claimant and Respondent agreed that the date of implementation of revised norms is 1/10/1996 and disputed the claim in entirety. The Respondent also raised counter claim of Rs.88,077,746.00 being the money excessively paid and lying with the Claimant.