(1.) Two intriguing questions arise for consideration in this writ petition. Can the respondents initiate revenue recovery measures for alleged damages caused on account of re-tendering of the work awarded to one Late T.P Paulose? Secondly, even if it is held so, can the legal heirs of the Late T.P.Paulose be held liable to the alleged damages caused to State exchequer.
(2.) Sri.T.P.Paulose, a contractor, was the successful tenderer in terms of Ext.P1 notice inviting tenders for providing rain shade to the court complex at Muvattupuzha. Ext.P1 is dtd. 7/10/2016. Sri.T.P.Paulose on 20/10/2016 addressed to the 2nd respondent requesting to relieve him from the obligation to complete the work, which was awarded to him. Despite this notice, the 2nd respondent proceeded to select late Sri.T.P.Poulose as lowest tenderer pursuant to Ext.P1 notice on 28/10/2016. As per Ext.P4 dtd. 14/12/2016, late Sri.T.P.Paulose was put on notice that his failure to execute agreement will entail further consequences and proceedings against him. Thereafter, on 30/1/2017, the attempt of the 2nd respondent to persuade the second lowest bidder to complete the work failed, and therefore, proceedings for recovery against Sri.T.P.Paulose was recommended. It is pursuant to this order that Ext.P6 was issued to late Sri.T.P.Paulose stating that an amount of Rs.6,01,929.74 was the loss caused to the Department consequent to the re-tendering of the work. In response to Ext.P6, late Sri.T.P.Paulose addressed to the 2nd respondent on 29/7/2017 vide Ext.P7 stating that he is not liable under any circumstances for the loss that was caused. It is pertinent to note that Ext.P6 was dtd. 8/6/2017 and by Ext.P8, the said request was turned down and the 2nd respondent decided to proceed with recovery measures against late Sri.T.P.Paulose. By order dtd. 11/7/2022 in I.A.No.1/2022, his legal heirs were impleaded as additional petitioners 2 to 4, who are prosecuting the present writ petition.
(3.) A counter affidavit has been filed on behalf of the 2nd respondent in which it is contended that as per notice inviting tender for the works, every bidder is expected before quoting his rate to inspect the site of the proposed works. It is also stated that the rates quoted shall be inclusive ones, covering all the operations contemplated in the specifications and tender schedules and all incidental works necessary for such operations such as shoring bailing out work, scaffolding etc. Therefore, it is contended that since late T.P.Paulose carried out joint inspection with officers of the respondent and found that various items involved in the work were not provided in the price schedule and that the petitioner had not inspected the site before quoting the tender. It is further averred that if the contractor does not come forward to execute the original agreement after the work is awarded, the selection notice issued in his favour gets cancelled and, hence, a breach is committed by him.