(1.) AGGRIEVED by judgment dated 29th September, 2010 in W.P.(C) No.28884 of 2010 the unsuccessful petitioner therein preferred this writ appeal.
(2.) THE appellant was the successful bidder for execution of a work of laying underground cable from the 110 KV Substation, Iritty to Iritty Town. THE said work was required to be completed within a period of three months from the date of execution of the contract. THE contract itself was required to be entered into within a period of three days from the date of declaration of the successful tender. For various reasons, the appellant admittedly could not enter into the contract. THErefore the respondents cancelled the decision to award the contract in favour of the appellant and proceeded to re-notify and invite fresh tenders for execution of the said work.
(3.) WHEN the matter is taken up, we are informed that pursuant to the notification inviting fresh tenders dated 16.9.2010 a third party has already been awarded the contract and the third party entered into a written agreement with the respondents.