(1.) The Arbitration Request relates to the dispute in respect of construction of Edappally Railway Over bridge between km. 436/380 and km. 438/350 of National Highway 47.Though the tenders were invited and accepted in 2005 and though the period for completion of the contract was 24 months, even now the work is not completed, which adds to the misery of the travelling public. The applicant prays for appointing an arbitrator for resolving the dispute mentioned in the Arbitration Request. The Respondents contend that going by the terms of the contract, the dispute is not an arbitrable dispute.
(2.) On 27.1.2005, the applicant submitted tender, above 25.95% of the estimate rate based on 1999 PWD schedule of rates. The tender was accepted as per Annexure Al letter of acceptance dated 21.7.2005. According to the applicant, the possession of the work site was handed over on 2.9.2005. The period for completion of the contract expired on 1.9.2007. According to the Petitioner, he has done a major part of the work. This is denied by the Respondents. According to them, only 41 % of the work was completed as on 22.12.2007, based on the original contract price. Based on the revised contract price, the progress achieved was only 30% as on 22.12.2007. According to the Respondents, the work carried out from 22.12.2007 to 1.3.2009 was only 12% as against 70% target.
(3.) A supplemental agreement was executed between the parties. According to the applicant, a sum of Rs. 1,18,87,265/- payable to him was withheld by the opposite parties and as a condition for releasing the amount, he was compelled to execute the supplemental agreements. The applicant sought extension of the period for completion of the work. It is stated by the learned Counsel for the applicant that extension was granted up to 1.3.2009. On 7.3.2009, the applicant requested for appointment of a Dispute Review Expert as stipulated in Clause 24 of the General Conditions of Contract. On 9.5.2009, the applicant again made a request for appointment of Dispute Review Expert and also for extension of the "intended completion period". In the letter dated 10.6.2009 issued by the applicant to the Chairman of the Council of Indian Roads Congress, it was stated thus: