LAWS(DLH)-1994-2-8

SUNEHRI LAL Vs. UNION OF INDIA

Decided On February 08, 1994
SUNEHRI LAL Appellant
V/S
UNION OF INDIA Respondents

JUDGEMENT

(1.) The present writ petition has been filed by the petitioner to impugn the order dated September 19, 1981, passed by the Joint Secretary, Land and Building, which is annexure A to the petition.

(2.) The petitioner was owner of a plot of land. which was situated at Karkardooma. This land of the petitioner was acquired by notification issued under Section 4 of the Land Acquisition Act. 1894 on November 13, 1959. The land was finally acquired vide Award No. 54A of 1970-71 given by the Land Acquisition Collector in 1971. The petitioner was left with no other land after this acquisition and he applied that he should be given a plot of land for residential purposes, as his land was acquired by the Government. He made an application dated March 20. 1975. to the Delhi Administration, Delhi, and received a reply dated September 29, 1975.to the offect that the case of the petitioner for an alternalive plot can be processed further only when the compensation is offered/paid to him by the Land Acquisition Cellector/District Magistrate. Delhi. The petitioner was requested to intimate when the same was done to enable the Department to process his case for allotment. The petitioner received a copy of the letter dated May 1, 1978, which was addressed to the Land Sales Officer, Delhi Development Authority, Vikas Minar, New Delhi, by the Under Secretary, Land & Building Department, Delhi Administration, Delhi, wherein a request was made to allot the land measuring 125 sq. yds. to the petitioner Sunehri Lal. The petitioner thereafter received another letter on February 26, 1979,and he was intimated that he was found eligible for allotment of an alternative developed land on perpetual lease basis in the Delhi Development Authority's East Zone Residential Scheme measuring 104 sq. metres approximately. He was further intimated that's that plot was not available he was being offered another plot in lieu of the same and the premium was fixed atRs.9,418.00 i.e. Rs. 73.00 per sq. mtrs. This offer was made to the petitioner for and on behalf of Deputy Director (R), Delhi Development Authority, Annexure 'D' to the writ petition. The offer was accepted by the petitioner on March 19, 1979,and he submitted a Bank Draft for Rs. 2.355.00 us well as the requisite affidavit. The petitioner thereafter was intimated by letter dated April 20, 1979, that the draw of specific plot number will be held on April 25. 1079 ;at 3 P.M. in the room of Executive Oflicer(R) on the First floor at Vikas Minar. The Land and Sales Officer. Delhi Development Authority, addressed another communication on June 5, 1979 to the petitioner asking him to deposit within one month from the date of issue of the letter a sum of Rs.6,780.20 and Hie details are referred to in paragraph 2 of the above said letter, which reads as follows:- "You are now requested to deposit within one month from the date of issue of this letter a sum of Rs.6780.20 (Rupees Six thousand seven hundred eighty and paise twenty only) as per detailed below by demand draft in favour of the Delhi Development Authority.

(3.) The petitioner wrote a letter dated July 3, 1979 requesting some more further lime to deposit the balance amount and such request was accepted by the respondents and ultimately the possession of plot No.30.Block B. Measuring 122.47 sq. metres, Jhilmil Tahirpur Residential Scheme Phase II was given to the petitioner and possession was also handed over. This is evident from the letter dated September 14, 1979 (annexure H), which was addressed to the petitioner by the Deputy Director. Delhi Development Authority. The lease-deed in respect of the plot was executed along with the site plan in favour of the petitioner on July 13,1980. Copy of the lease-deed forms part of the record of this case (annexure 'K'). The petitioner, accordingly, has paid full consideration for the allotment in his favour. The possession was handed over to him and the lease-deed has also been executed. His reiterated that the plot in question is in his physical possession and he is the lawful occupant. The respondents on September 19, 1981, withdrew the confirmation of the recommendation made by the respondents for an alternative allotment in favour of the petitioner on the ground that he had purchased the notified land.