(1.) The Delhi Development Authority, respondent No.1, awarded a contract for construction of 136/188 CSP Houses at Paschim Vihar, Pocket, GH-6, Near Nangloi Sayed Village, to the petitioner, M/s.Enkay Construction Company. A formal contract bearing N0.21/EE/WD-6/89-90/DDA dated 30.9.1989 was executed. The construction of houses could not be completed within the stipulated time frame. The petitioner attributed the delay in completion of construction work to acts of commission/omission on the part of respondent No.1. On completion of work, the petitioner sought release of outstanding dues. The respondent No.1, however, failed to pay the same. Thus, disputes and differences arose between the parties.
(2.) By way of a letter dated 23/1/1995, the petitioner requested the Engineer Member of respondent No.1 to refer the disputes/differences to arbitration in terms of Arbitration Clause 25 of the General Conditions of Contract. The Engineer Member, however, according to the petitioner, 'refused and deliberately neglected' to refer the disputes to arbitration and, thus, abdicated his power to appoint an arbitrator. The petitioner, accordingly, approached this Court by way of a petition under Section 20 read with Section 8 of the Arbitration Act, 1940 for appointment of an arbitrator.
(3.) Opposing the petition for appointment of an arbitrator, the respondent No.1 asserted that the stipulated date of completion of work was 29th of September, 1990, but the petitioner could accomplish the same on 20th of January, 1997 only. It is claimed that the payment for the entire work done was made to the petitioner up to the final bill in accordance with the terms of the contract, and the petitioner accepted all payments in full and final settlement without any protest. According to the respondent No.1, no disputes/differences actually existed, and there was, thus, no occasion for a reference to arbitration. It is added that the respondent No.1, by its letter dated 23.3.1995, informed the petitioner that since its request for arbitration had been received in its office on 23rd of January, 1995, after expiry of the time prescribed under Clause 25 of the agreement, being barred, its claims were deemed to have been waived.