(1.) In this appeal M/s. M.L.Mahajan (hereinafter referred as the Contractor) has assailed the judgment of the learned Single Judge dated 20/07/1990 whereby the 'Award of a sum of Rs.2,21,600.00 in respect of Claim No.20 (which was for a total sum of Rs.4,60,000/-) had been set aside. This Claim was lodged on account of the alleged rise in the market price beyond the stipulated date of completion. The Appellant/Contractor has prayed that the Award dated 15.9.87, in respect of Claim No.20, be made rule of the Court and that interest thereon at the rate of 18% per annum from the date of the Award till the date of the payment be also granted along with costs. The facts in brief are that the Contractor was awarded the work of construction of 40 MIG/LIG and 20 Janata Houses at Dilshad Garden, Group A, Pocket II, Delhi, vide letter dated 25.3.1977. Thereafter an Agreement bearing No. 6/HD/XIX/76-77 dated 31.3.1977 was executed between the parties. The work was to commence on 4.4.1977 and was to be completed by 3.8.1978, i.e. 16 months. As it transpired, the project was completed as late as in August 1980, i.e. after a delay of approximately 24 months.
(2.) The Contractor invoked arbitration by his letter dated 29.9.1982. After one year, the Engineer Member of the DDA appointed Shri R.L.Hans, S.E.DDA, as the Arbitrator who however, resigned in December, 1985. Thereafter, the Engineer Member, DDA, in terms of his letter dated 9.1.1986, appointed Shri G.R. Hingorani, Chief Engineer, DDA, as the Arbitrator and referred to him the 24 Claims raised by the Contractor. The Arbitrator made and published his Award on 15.9.1987. He disallowed the Claims 3,6,7,9 to 18, 21 to 24. In other words, out of 24 Claims only seven were allowed in varying amounts. Under Claim No.1 an amount of Rs.54,279.00 was awarded, although Rs.1,20,000.00 was claimed; under Claim No.2, for the release of Bank Guarantee, was allowed; under Claim No.4 an amount of Rs.8250/- was awarded against the claim of Rs.16,500/-; under Claim No.5, an amount of Rs.5,380.00 was awarded against the claim of Rs.45,000.00; under Claim No.8 an amount of Rs.3,938.00 was awarded against Rs.4000/-; under Claim No.19 a sum of Rs.9000.00 was awarded for keeping the Bank Guarantee alive beyond the stipulated date of completion. Interest at the rate of 18% was awarded from 29.9.1982 upto the date of payment or decree whichever was earlier. As has already been indicated above, in this Appeal the Contractor has only prayed for the restoration of the sum of Rs.2,21,600.00 awarded in Claim No.20 i.e. "on account of rise in the market price beyond the stipulated date of completion."
(3.) The Arbitrator has dealt with Claim No.20 in the following words :