(1.) M/s. Skipper Towers Pvt. Ltd, the petitioner company, is a well known builder of Delhi. In C.W. 2371/89 the petitioners had taken in auction a commercial plot from the DDA in Jhandewalan Block, known as Commercial Tower in 1980. Till 1990 they had not made payment of over Rs. 8 crores to the DDA. Through the W.P. in this Court they secured the sanction of the building plan and permission to undertake the construction. It was ultimately found that they had not only not made the payment of over Rs. 8 crores for a decade but also violated the Agreement and the Licence Deed thoroughly. This Court dismissed the W.P. and permitted the DDA to enter the property after forfeiting the entire amount initially paid. The present W.P. is not only a repeat story by the same builder but worse. Here there is not only breach of Agreement and the Licence Deed but breach of solemn undertaking to this Court regarding payment. The petitioners are guilty of contempt of this Court. DDA Auction of Commercial plot. If bid of a builder (a previous defaulter) is accepted on 9.2.82 requiring him to pay balance within 90 days and DDA grants to him repeatedly extentions for more than 3 years during which he pays sonic amount and then he obtains extentions from High Court in W.P. by giving undertaking to pay balance dues and fails, then he is guilty of Contempt of Court. If same builder has defaulted for a decade of Rs. 8 Crore about Jhandewalan plot, then he is not entitled to relief u/Art. 226.
(2.) On 9.2.1982 the petitioners successfully bid for plot No. 12, Community Centre, Yusuf Sarai,N Delhi, measuring 225 sq. meters for construction of a multistoreyed commercial complex, for Rs. 84 lakhs. The petitioner paid 25% of the bid amount immediately. According to the terms of the auction the balance of 75% was to be paid within 90 days from the date of auction. In spite of two extensions the balance amount was not paid. The DDA, therefore, informed them on 4.6.1982 that their bid was cancelled. On their further request, however, on 9.11.1982 the DDA rescheduled the payment of the balance amount together with interest. The payment schedule was again readjusted on 14.11.1984. On 13.9.1985 a fresh Agreement was made between the DDA and the petitioners on the faith and representation made by the petitioners. According to the Agreement the petitioners were to make the payment of 50% of the auction premium before the Agreement was signed and the balance was to be paid with 18% interest in three equal instalments payable on 15.9.85, 15.12.85 and 15.6.86. For the balance of the amount the petitioner was to give a bank guarantee. On the same day a Licence Deed was executed by the petitioner for a period of one year. The Licence Deed made it clear that the legal ownership of the plots hall remain with the DDA. Any conssonable probability or chance of the accused heme found guilty of the offence alleged. truction to be made by the petitioner was to conform to the rules, regulations, bye-laws, orders and directions issued by the DDA from time to time. The petitioners were prohibited from making any transfer of the premises. During the period of Licence the Licensor had a lien on the belongings and property of the petitioners. The Licence Deed further provided that in case of breach by petitioner the DDA had absolute discretion to revoke the licence and enter the plot and take it over, free from all encumberances, alongwith all buildings that may be standing therein without payment of any compensation. The Licence Deed was subject to the sole arbitration of the Vice-Chairman, DDA, in case of any dispute. At the time of the Agreement the petitioners made the payment of Rs. 20 lakhs so as to complete the 50% of the payment of the auction premium. The possession of the plot was delivered to the petitioner on 8.10.1985. The petitioners did not make the payment of any further instalments and tried to avoid giving the bank guarantee.
(3.) Thus, the petitioner availed of the indulgence shown by the DDA from time to time and secured possession of the plot, without, making the payments and subsequent instalments, as agreed. As in the earlier petition it did not prefer to avail of the arbitration clause in the Licence Deed and proceeded to file the present W.P. in May, 1988. After the petition was filed, this Court again rescheduled the terms of payment while giving the direction to the petitioners to make the payment according to the schedule and simultaneously directing the DDA to sanction the plan and permitting the petitioner to start the construction. The petitioners failed to make the payment and to furnish the bank guarantee, as required by the orders of this Court. While sanctioning the Plan the petitioners were informed by the Chief Fire Officer to comply with the requirements of fire safety. The petitioners constructed the basement and 6 floors of the building in breach of the building bye-laws and safety regulations required by the Chief Fire Officer. While the construction was being done by the petitioners, they deliberately refused to make any payment of the instalments, as directed by the Court. On 22.3.90 the Bench hearing the petition took an undertaking from the petitioners to make the balance payment in two instalments, also clarifying that the failure to make the payment would amount to contempt of Court. There-after the Cheque for Rs. 20 lakhs was given by the petitioners to the DDA. The Cheque bounced.