(1.) We have heard learned counsel for the parties.
(2.) The matter arising out of a dispute in execution of a works contract was referred to the Arbitrator by the High Court on 4.09.2008. The Arbitrator made his Award dated 10.07.2010 in favour of the appellant. It was challenged under Section 34 of the Arbitration and Conciliation Act, 1996 ("the Act") before the Seventh Additional District Judge, Bhopal by the respondent-State of M.P. The respondent sought to amend its objections after three years which was rejected by the trial Court. On a petition under Article 227 of the Constitution of India, the High Court has allowed the said amendment.
(3.) Learned counsel for the appellant submitted that the amendment could not be allowed beyond the period of limitation which affected the vested rights of a party. It was also submitted that the objection having not been raised under Section 16(2) of the Act before the Arbitrator, could not be raised under Section 34 of the Act. In support of this submission reliance has been placed on MSP Infrastructure Ltd. vs. Madhya Pradesh Road Development Corporation Ltd., 2015 13 SCC 713.