(1.) Leave granted in Special Leave Petition No. 1457 of 1986.
(2.) The respondents were granted mining leases under Rule 31 of the A. P. Mining Rules, 1966. The Forest Conservation Act, 1980 (for short 'the central Act') had come into force on 25/10/1980. Subsequently in terms of the grant of the lease the respondents applied for renewal. The State government refused to grant renewal in view of the prohibition contained in Section 2 of the Act. The respondents filed the writ petitions in the High court and the division bench in the impugned judgment dated 9/6/1982 directed to consider the renewal of leases of the respondents and seek approval of the central government under Section 2 of the Act. Calling in question the legality of the directions issued by the High court these appeals by special leave have been filed. In some of the cases the application for renewal has been filed after the Act had come into force but on the question of law it does not make much difference. The point raised is no longer res Integra. This court in Ambica Quarry Works v. State of Gujarat held that when a public authority is vested with the power, the expression 'may' has been construed as 'shall' because if the conditions for the exercise of the power are fulfilled, it is coupled with a duty. When the grant of renewal was sought to be made then the authority has been invested with the duty to grant renewal. On the facts and circumstances in these cases specially in view of the prohibition contained in the Act renewal cannot be granted since the Act had come into force. So any grant of renewal should be consistent with the provisions contained in the Act. The purpose of the Act is conservation of forests and to prevent the depletion of forests. In other words the Act intended not only to protect the existing forests but also to conserve and protect the existing forests in accordance with the provisions of the Act. In view of the prohibition for grant of lease in the reserved forest area, grant of renewal in the face of the prohibited area will be in violation of law. Therefore, the authorities though had the power, but had duty while conserving the forest to refuse to grant renewal, In that view the government's refusal to grant renewal, therefore, cannot be said to be illegal. If they consider that renewal could be granted, even then the prior approval of the central government is mandatory under Section 2 of the Act. The renewal cannot be granted in view of the prohibition contained in the Act, Therefore, the direction issued by the High court is clearly in violation of the statute and no mandamus or direction could be issued to violate the mandatory provisions of the Act. The direction accordingly is illegal. The appeals are allowed and the order of the division bench of the High court is set aside but in the circumstances without costs.