LAWS(SC)-1961-5-19

HARI SHANKER LAL Vs. SHAIRTBHU NATH

Decided On May 04, 1961
HARI SHANKER LAL Appellant
V/S
SHAIRTBHU NATH Respondents

JUDGEMENT

(1.) This appeal by certificate raises a question of construction, of R. 3 of the First Schedule to the Arbitration Act, 1940 (10 of 1940) (hereinafter referred to as the Act),

(2.) The facts material to the question raised may be briefly stated. The appellant and respondents 1 and 2 are brothers. On August 17, 1948, the appellant and respondents 1 and 2 and their mother by a registered deed of agreement referred their dispute regarding the partition of two house in the city of Banaras to two arbitrators, respondents 3 and 4. Within 10 days of the reference, the said arbitrators gave notice to the parties and began to take evidence i.e., they entered on the reference. On July 25, 1949, Rajwanti the mother of the appellant and respondents 1 and 2 died, and the arbitrators did not proceed with the inquiry. On August 31, 1950, i.e., more than one year after the death of Rajwanti, the appellant gave a notice to the arbitrators requesting them to proceed with the reference and give the award at an early date. On October 1, 1950, i.e., within 4 months from the date of the notice, the arbitrators made an award and it was duly registered . On January 23, 1951, the appellant filed an application under Ss, 14(2) and 17 of the Act in the Court of the Civil judge, Banaras, praying that the said award be filed and be made a rule of the court. The said application was registered as a suit; the appellant was placed in the position of plaintiff and the respondents in that of defendants. The respondents raised various objections to the said application; one of the objections, with which only we are now concerned, was that the award was not given within the time fixed by law. The learned Civil Judge rejected the objections and made a decree in terms of the award. On appeal the High Court came to the conclusion that the award was made after the expiry of the period of limitation, and on that finding set aside the decree of the learned Civil judge and dismissed the suit with costs. Hence this apple.

(3.) Learned counsel for the appellant contends that R. 3 of the First Schedule to the Act provides for alternative periods within which arbitrators have to make their award, that under the second alternative an award could be made within 4 months from the date of notice issued by a party calling upon the arbitrators to act, and that, as in the present case the notice to act was given by the appellant to the arbitrators on August 31, 1950 the award made by them on October 3, 1950, was within the time prescribed.